Day after day, we gain kWh improving many small details. Thus, the screw almost identical to ours supplied by the same manufacturer, put on the Thames in Windsor have an efficiency of about 50% as we reach 70% with the goal of reaching 75%. At Windsor, the operator screws, David Chambeau senior engineer trained in Silicon Valley, is very knowledgeable but did not have time to observe daily how the central in the details. A Heudreville we do daily commonsense observations and test small changes.
After two years, we believe that working together the companies that participated in Heudreville project with David Chambeau who built other central screw on new sites would reduce the minimum initial investment and facilities improve yields screw until 85%. We could equip profitably much larger but also much other smaller sites.